Introduction

The Natt is a 400 ft WD rated offshore Jackup rig, managed and owned by Borr Drilling. The Rig was commissioned at PPL shipyard PTE Ltd. in Singapore in 2018.

The Rig is endowed with mordern offshore drilling capabilities with an accommodation capacity of 150 persons.

The Natt arrived Anyala soft pin location on 31st March 2019 ang it began operations on the 17th April 2019 on Anyala II location.

The first well delivered by the Natt Rig for E&P. The well was spudded on the 5th May 2019. It was successfully drilled and abandoned on the 8th August 2019.

The rig was towed to the ANDP-1 location on 17th August 2019 and NATT was utilized to install a conductor supported platform (CSP) in October 4th 2019. The first phase (Phase 1) of Anyala West batch drilling operations kicked off on the 4th October 2019. The first well in the series of 4 batch wells, AW55B was spudded to ANY-012A at 1430hrs on the 9th October 2019.